We are now able to irrigate 4-6 blocks per shift with
one dam pump only. The dam pump is delivering 2.5-3 times more
water than before. The bore pump is being used to fill the front
dam.
The pruning of water shoots of the Manzanillo trees is continuing
and there are12,000 Manzanillo trees more to go.
We have replaced laterals and sprinklers of four Manzanillo blocks
and another two blocks are to be done in July.
We have completed a fertigation of 16 front blocks with the
remaining Quickstart (nitrogen, phosphorus, potassium, boron etc),
Copper and Zinc.
Unfortunately due to a delay of the contractor,
16,000 trees are scheduled to be removed early in July.
Vladimir Belodedenko
Manager
Keetah Grove